Refurbishment of the ground & first floors

Value: £640,000

Duration: 18 Weeks

Description of Works:

The ground floor included new mechanical and electrical installation incorporating A/C s to all new classrooms. New major refurbishment with new teaching layouts to the engineering workshop, machine shop, and sixth form common room with Blue light technology.

The first-floor refurbishment included the creation of new class spaces plus modification to the existing. The creation of a new digital classroom and audio booth incorporating LED walls and corridor visual screens.