Completed

Value: £208,000

Duration: 6 Weeks 

Description of Works:

Due to water ingress from below the existing concrete slab, it was necessary to remove the existing floor substructure. This included an asbestos bitumen underlayer which needed to be scrabbled back to the existing slab. All Partitions were dismantled and erected after the DPM application was laid over an area of 400m2. We added new vinyl flooring and partition walls alongside a refurbishment WC with new IPS sanitary ware and cubicles. This project was completed over the 6-week summer term and involved out of hours working to ensure completion.